Day 3 of the ARCHER2 Build


Day 3 and significant progress has been made. Yesterday saw the fitting of the cooling infrastructure between the mountain cabinets and the CDU. The site’s water supply has now been connected, bled and made live.

Cooling Infrastructure

All the power connections have been made and the CDU has been powered up as a functional test.

Power connectors and plugs

The overhead trays have also been fitted and work has begun on connecting the management server.

Cabinets with and without overhead trays

Watch out for tomorrow’s blog for more details on today’s progress.

Pictures supplied by Greg Muir